The City of Alameda Public Works Department is requesting proposals for environmental soil investigation, remediation action plan, reporting; preparation of cost estimate, construction plans, specifications, and permitting.
The City desires to obtain the services of environmental firm to prepare a remediation work plan, conduct additional soil and groundwater investigation activities, preparation of a letter report presenting investigation findings, and a completion of a remedial action plan; preparation of engineering cost estimate, project schedule, construction plans, specifications, and permitting. The goal of this investigation is to define the extent of the contaminated soil and groundwater at within the site and to prepare a remedial action plan, reporting; preparation of cost estimate, construction plans, specifications, and permitting for the necessary soil remediation.
Proposed Selection and Project Schedule.
Proposal Due Date: February 4, 2016
Award of Agreement: April 5, 2016
Projected Agreement Start Date: April 19, 2016
End of Contract: June 30, 2016
PROPOSAL DUE DATE AND DELIVERY:
Three (3) sealed copies of the proposal, clearly marked with the project description, should be submitted no later than:
2:00 PM, February 4, 2016
to the address below. All copies received by that time will be date and time stamped. Proposals will not be accepted after this time. Proposals should be addressed to:
Abdulla Ahmed, Project Manager II
Public Works Department
950 West Mall Square, Room 110
Alameda CA 94501
FAXed or emailed proposals will not be accepted. Hand carried proposals will be accepted at the above address.